Project J-2 Construction Pictures - April 2018

Project J 2 Left 2Project J 2 Middle 1

                                                         Project J 2 Right

Crews have placed beams for the new exit from US 290 outbound to Dacoma/Mangum. (top left) They have also placed beams for the US 290 outbound mainlanes just past the I-610 West Loop. (top right) Closer to Dacoma, crews have placed concrete panels over the outbound mainlane beams and will next place steel rebar and concrete on top. (bottom)

 

 