Project G Construction Pictures - March 2014

Project G Outbound US290 FR.WLY Brdg and NorthboundProject G Outbound US290 FR.WLY Brdg and Northbound 22

The picture on the left shows crews working on the new outbound US 290 frontage road just before Beltway 8.
At right, the contractor works on a column for the new northbound Beltway 8 frontage road. It will go up and over the Union Pacific railroad tracks, keeping motorists from having to use Senate Avenue as is the case today.

Project I Construction Pictures - March 2014

Project I-Pinemont Bridge West and EastProject I-Pinemont Bridge West and East14

These images are of crews beginning work on the new Pinemont Bridge, which will go over US 290. The contractor demolished the old bridge in March 2014.

Project J-1 Construction Pictures - March 2014

Project J-1 Outbound US290 FRProject J-1 US290 Outbound FR10

Here the contractor puts finishing touches on the outbound US 290 frontage road just before W. 34th Street. That frontage road, from the I-610 interchange to W. 34th, was opened to traffic in April 2014.

Project K Construction Pictures - March 2014

Project K-Dir Conn D Night Beam Hanging4Project K-Dir Conn D Night Beam Hanging10

These are pictures of the contractor hanging beams at night for the new direct connector from westbound I-610 to westbound US 290. Work is anticipated to be finished on this direct connector by the end of May 2014.

Construction Picture Archive