Project A Construction Pictures - July 2017

Project A

The contractor has poured half of the new westbound mainlane pavement between FM 2920 and Field Store.

Project B Construction Pictures - July 2017 

Project B LeftProject B Right

Newly poured concrete barrier for the westbound mainlane bridge over Roberts Road. (left) Crews placed bondbreaker for the new eastbound exit to Bauer Road, later they will place steel rebar and concrete on top to complete the exit. (right)

Project C-1 Construction Pictures - July 2017 

Project C 1

A crew works on a signage column above the ground along US 290 westbound near Mason Road. 

Project C-2 Construction Pictures - July 2017 

Project C 2 LeftProject C 2 Right

The contractor has placed new westbound sign structures at Fairfield Place (left) and at SH 99 (right).

Project D Construction Pictures - July 2017 

Project D

The contractor digs where new storm sewer will be placed along the US 290 westbound frontage road near Cypress Creek.

Project E Construction Picture - July 2017 

Project E Picture 

The contractor builds the steel rebar cage to form the supporting bridge column at FM 1960.

Project F Construction Picture - July 2017 

Project F Picture 

Crews placed bridge beams between West Road and Eldridge Parkway for the widened US 290 westbound mainlanes.

Project H Construction Pictures - July 2017 

Project H Picture

Crews pour concrete on the concrete railing on US 290 eastbound over Cole Creek. (left) The contractor constructed supporting bridge columns for the eastbound mainlanes over Gessner. (center) Motorists travel on new pavement in the center portion of the freeway while the contractor continues to work on the eastbound mainlanes. (right)

Project I Construction Pictures - July 2017 

Project I LeftProject I Right

The contractor welds together pieces of steel rebar which will ultimately form the railing for the US 290 eastbound mainlane bridge over Antoine. (left) Crews placed several panels for the sound wall along US 290 westbound near W. 43rd. (right)

Project J-1 Construction Picture - July 2017 

Project J 1 Picture 

A new U-turn will be constructed on the I-610 West Loop northbound frontage road at W. 18th.

Project J-2 Construction Pictures - July 2017 

Project J 2 LeftProject J 2 Right

Beams for the US 290 eastbound mainlane bridge over Mangum from above, (left) and from the street below. (right)

 

Construction Picture Archive