Project A Construction Pictures - April 2018

Project A Picture

The contractor repairs the inside curb along the outbound frontage road near Hegar. Work on this project is substantially complete.

 

Project B Construction Pictures - April 2018

Project B LeftProject B Right

Crews complete placing concrete between the outbound mainlanes and frontage road at Badtke. (left) The contractor has completed placing sod between the outbound mainlanes and frontage road at Roberts/Katy-Hockley. (right) Work on this project is substantially complete.

 

Project C-1 Construction Pictures - April 2018

Project C 1 LeftProject C 1 Right

The contractor lays asphalt for the new outbound frontage road between Mueschke and Mason. (left) Just east of there, the contractor has completed a portion of the bridge structure for the outbound frontage road over Fairfield Channel. (right)

 

Project C-2 Construction Pictures - April 2018

Project C 2 Picture

Crews build a drainage outfall near Bauer. Work on this project is substantially complete.

 

Project D Construction Pictures - April 2018

Project D Left

The contractor has placed down base material for the outbound frontage road between Barker Cypress and Skinner. Later asphalt, steel rebar and concrete will be placed on top.

 

Project E Construction Pictures - April 2018

Project E LeftProject E Right

Crews demolish the existing inbound mainlane pavement between Telge and Huffmeister. (left) Traffic along FM 1960 between Eldridge and US 290 has been moved to the center of the roadway, to allow the contractor to begin building the new FM 1960 frontage roads. (right)

 

Project F Construction Pictures - April 2018

Project F LeftProject F Right

The contractor completed placing steel beams for the new T-Ramp from the Northwest Station Park and Ride to the METRO HOV lane, this work is anticipated to be completed in July 2018. (left) The contractor has also completed placing placing beams for the new outbound mainlanes just before Jones. (right)

 

Project G Construction Pictures - April 2018

Project G Picture

Construction on this project is substantially complete.

 

Project H Construction Pictures - April 2018

Project H LeftProject H Right

The contractor has placed beams for the inbound mainlane bridge over Fairbanks North Houston. (left) Crews have poured most of the inbound mainlane pavement in this project. (right)

 

Project I Construction Pictures - April 2018

Project I LeftProject I Right

Crews pour concrete for the middle portion of the mainlanes near W. 43rd. (left) They have poured most of the middle mainlane pavement in this project. (right)

 

Project J-1 Construction Pictures - April 2018

Project J1

The contractor has begun pouring concrete for the I-610 West Loop north- and southbound U-turn lanes at W. 18th, they are shown in pink on this picture.

 

Project J-2 Construction Pictures - April 2018

Project J 2 Left 2Project J 2 Middle 1

Project J 2 Right

Crews have placed beams for the new exit from US 290 outbound to Dacoma/Mangum. (top left) They have also placed beams for the US 290 outbound mainlanes just past the I-610 West Loop. (top right) Closer to Dacoma, crews have placed concrete panels over the outbound mainlane beams and will next place steel rebar and concrete on top. (bottom)

 

Project K Construction Pictures - April 2018

Project K Picture

Construction on this project is substantially complete.

 