Project C-1 Construction Pictures - August 2018

Project C 1 LeftProject C 1 Right

The contractor surveys newly placed steel rebar which will reinforce concrete for the widened outbound frontage road before Mason. (left) Crews work to complete Mason Road at US 290. (right)

Project D Construction Pictures - August 2018

Project D LeftProject D Right

Crews place new storm sewer underneath the middle portion of the mainlanes before Skinner. (left) This month the contractor placed new street signage along the entire project limits, from Telge to Mueschke. (right)

Project E Construction Pictures - August 2018

Project E LeftProject E Right

The contractor placed beams, then concrete panels on top of the beams, for the inbound mainlane bridge over Huffmeister. (left) Crews have also poured concrete for the inbound mainlanes between Telge and Huffmeister. (right)

Project F Construction Pictures - August 2018

Project F Picture

The contractor continues to make progress on the outbound mainlanes between Jones and West.

Project H Construction Pictures - August 2018

Project H LeftProject H Right

Crews anticipate opening the outbound mainlanes in this project, from Pinemont to W. Little York, in September 2018. (left) After resolving several utility conflicts, the contractor is now building the outbound frontage road between Pinemont and W. Tidwell. (right)

Project I Construction Pictures - August 2018

Project I LeftProject I Right

With the mainlanes complete in this project, the contractor is focusing on cross-street intersections such as Antoine. (left) Crews are also rebuilding Milwee Street between Antoine and the inbound frontage road. (right)

Project J-1 Construction Pictures - August 2018

Project J 1 Picture

In the middle of this picture is the direct connector from I-10, which opened this month in its final configuration. Two lanes go to I-610 eastbound, and two lanes go to US 290 outbound.

Project J-2 Construction Pictures - August 2018

Project J 2 LeftProject J 2 Right

The contractor has completed most of W. 34th under US 290, (left), as well as most of Mangum under US 290 (right) The mainlanes in this project are complete.

Construction Picture Archive