Project A Construction Pictures - December 2018

project a ebml at ke k6ckG

Work on this project is substantially complete.

Project B Construction Pictures - December 2018

project b wbml at ro VCanu

Work on this project is substantially complete.

Project C-1 Construction Pictures - December 2018

Project C 1 LeftProject C 1 Right

Crews work to complete the outbound frontage road between Mueschke and Mason. (left and right) They finished this work in January 2019, and began working on the outbound mainlanes in this area.

Project C-2 Construction Pictures - December 2018

project c 2 picture

Work on this project is substantially complete.

Project D Construction Pictures - December 2018

Project D LeftProject D Right

The contractor poured more concrete over a drainage system on top of which the HOV lane will be located. (left) After the concrete was poured, a finishing machine smoothed out the concrete. (right) Once this work is completed, the mainlanes in this project can open in their final configuration.

Project E Construction Pictures - December 2018

Project E LeftProject E Right

Crews have opened up the four inbound mainlanes in this project, putting them in their final configuration. (left) That included inbound mainlane entrances and exits, which had been closed on occasion while the construction was occurring. (right)

Project F Construction Pictures - December 2018

Project F Picture

The contractor opened up a fifth outbound mainlane, placing the inbound and outbound mainlanes in their final configuration.

Project G Construction Pictures - December 2018

Project G Picture

Work on this project is substantially complete. This is the final US 290 mainlane configuration looking west at the US 290/Beltway 8 interchange.

Project H Construction Pictures - December 2018

Project H LeftProject H Right

With the mainlane and intersection construction completed on this project, the contractor is now finishing up tasks such as pouring sidewalk concrete along the inbound frontage road. (left and right)

Project I Construction Pictures - December 2018

Project I LeftProject I Right

The contractor is working to complete construction on cross street intersections such as Antoine. (left and right)

Project J-1 Construction Pictures - December 2018

Project J 1 Picture

Westbound W. 18th motorists cross the I-610 West Loop northbound frontage road. The contractor opened W. 18th underneath I-610 this past month.

Project J-2 Construction Pictures - December 2018

Project J 2 LeftProject J 2 Right

Dacoma northbound and southbound motorists drive on the northbound side of the street, as the contractor works to complete the northbound lanes. (left) Dacoma construction underneath US 290 was completed in January 2019. The contractor is also finishing Mangum under US 290, placing down median pavers is one of the last tasks to be completed. (right)

Project K Construction Pictures - December 2018

ProjectK

Work on this project is substantially complete.

 

Construction Picture Archive