Project C-1 Construction Pictures - October 2018

Project C 1 LeftProject C 1 Right

The contractor poured concrete for a portion of the outbound frontage road between Mueschke and Mason. (left) Crews placed down rebar for the frontage road in this area as well. (right) The outbound frontage road is anticipated to be completed in the first quarter of 2019. 

Project D Construction Pictures - October 2018

Project D Picture

Crews have placed drainage underneath an area between Telge and Mueschke where the HOV lane will eventually be located.  They are now working to complete the pavement over the drainage system.

Project E Construction Pictures - October 2018

Project E LeftProject E Right

The contractor has placed beams for the widened inbound mainlanes over SH 6/FM 1960. (left). The contractor has also placed beams for the new SH 6/FM 1960 bridge over US 290. (right)

Project F Construction Pictures - October 2018

Project F Picture

Crews completed pouring concrete for the outbound mainlane bridge over Jones. The outbound mainlanes from FM 529 to Eldridge Parkway opened in December 2018.

Project G Construction Pictures - October 2018

Project G Picture

Work on this project is substantially complete.

Project H Construction Pictures - October 2018

Project H Picture

With the mainlanes complete in this project, the contractor is now focusing on completing frontage road/cross street intersections. Here crews work on the outbound frontage road at Hollister.

Project I Construction Pictures - October 2018

Project I LeftProject I Right

With the mainlanes complete in this project, crews are focusing on completing the frontage roads and cross streets, including Antoine. (left and right)

Project J-1 Construction Pictures - October 2018

Project J 1 LeftProject J 1 Right

The contractor is almost ready to open the new I-610 northbound and southbound U-turns at W. 18th. (shown in pink at left) This will help mitigate congestion in the area when W. 18th is closed for reconstruction. (right)

Project J-2 Construction Pictures - October 2018

Project J 2 Picture

Crews are completing the new I-610 westbound exit ramp to the I-610 southbound frontage road (shown in pink), which will allow motorists to access Old Katy Road. This ramp opened in November 2018.